This project involved manufacture and installation of three staircases; two 20meter span footbridges with cladded roofs; all support columns and three cladded Lift Shafts. The project entailed Production of 3D model and fabrication drawings; value engineering; supply of materials; fabrication; all surface finishing to Network Rail N1 specification was undertaken in-house; supply and installation of a warm to touch approved Nylon Coated handrail system; supply and installation of woven stainless steel mesh; supply and installation of glazing; anti-slip coatings were applied by specialist approved sub-contractors in our workshops and the complete sections were transported to site; full contract lifting of steelwork during rail possessions enabled installation.